Update on Sitterly Road Bridge

April 14, 2022

 

A full closure of the Sitterly Road Bridge with the implementation of the full detour is required to remove temporary supports for the existing Temporary Bridge to allow for excavation for the new footings on the west abutment and center pier and to reset the temporary supports, which are in place to support the existing Temporary Bridge. This closure/work is being scheduled the week of April 18 through April 22, while local schools are on Spring Break. The detour will be posted with signs and will utilize Clifton Park Center Road, Route 146, Route 9 and Crossings Boulevard