Update on new water lines, McBride Rd, Hayner Rd, Lower Newtown & Button Rd

The new McBride Road water line has been approved by DOH and has been put in service.  Residents have received notice of the hook up policy if interested in hooking up to the Town water.  Hayner Road, Lower Newtown Road, and Button Road water line still in construction phase and is expected to be completed by Fall 2023.  A new 1 million gallon water tank is under construction on Button Road and is expected to be completed by the end of 2023.  Water Plant pump replacement project is under way with the demo of pump room #1.  New finished water pumps, chlorinators, and electrical is in process and will be completed by July 2023.  Finished pump room # 2 work will be started when room #1 is completed and in service, and then completed by the end of 2023.